Name of Project: Ishurdi-Baghabari 54 km 230 kV T/L Construction (Ishurdi Baghabari-Serajgonj-Bogra 230 kV T/L Project)
|
|
Objective:
|
|
|
Project cost:
|
|
|
Financed by:
|
Supplier's Credit |
Contractor Name:
|
M/s. TATA Power Company Lt. India |
|
Status
|
|
Physical:
|
100% |
Financial:
|
100% |
|
Contract sign on
|
06/30/2003 |
Completion date
|
03/29/2005 |
|
|
|
|
Name of Project: Joydevpur-Kabirpur-Tangail 78 km 132 kV T/L & 3 S/s Extn. Project (Joydebpur-Kabirpur-Tangail 132 kV T/L Project
|
|
Objective:
|
|
|
Project cost:
|
Local 2399.2312 lac taka, Foreign 896.13 lac taka |
|
Financed by:
|
DANIDA Mixed Credit |
Contractor Name:
|
JV of MT Hoggard & Lindpro, Denmark |
|
Status
|
|
Physical:
|
100% |
Financial:
|
100% |
|
Contract sign on
|
01/11/2005 |
Completion date
|
01/10/2007 |
|
|
|
|
Name of Project: Hasnabad & Tongi 230 kV and Kalyanpur 132 kV S/s Construction (Hasnabad-Aminbazar-Tongi & Haripur-Meghnaghat 230 kV T/L Project)
|
|
Objective:
|
|
|
Project cost:
|
Local 10909.351 lac taka, Foreign 4855.60 lac taka |
|
Financed by:
|
ADB |
Contractor Name:
|
Siemens Ltd. India |
|
Status
|
|
Physical:
|
100% |
Financial:
|
100% |
|
Contract sign on
|
08/24/2003 |
Completion date
|
05/23/2005 |
|
|
|
|
Name of Project: National Load Despatch Centre
|
|
Objective:
|
To establish modern central control of the network |
|
Project cost:
|
Local 37.89 MUS$, foreign 54.35 MUS$ |
|
Financed by:
|
ADB & JICA |
Contractor Name:
|
|
|
Status
|
|
Physical:
|
100% completed |
Financial:
|
|
|
Contract sign on
|
|
Completion date
|
06/30/2010 |
|
|
|
|
Name of Project: Shunt Compensation at Grid Substation by Capacitor Banks Phase-1
|
|
Objective:
|
To maintain reasonable voltage & to reduce Transmission loss. |
|
Project cost:
|
Local 6.53 M US$,Foreign 11.76 M US$ |
|
Financed by:
|
ADB |
Contractor Name:
|
|
|
Status
|
|
Physical:
|
100% |
Financial:
|
|
|
Contract sign on
|
|
Completion date
|
|
|
|
|
|
Name of Project: Aminbazar-Savar 132 kV Transmission Line
|
|
Objective:
|
To meet the growing demand of Savar area |
|
Project cost:
|
Local 2.16 M US$, Foreign 7.27 M US$ |
|
Financed by:
|
Dhaka PBS-1 |
Contractor Name:
|
|
|
Status
|
|
Physical:
|
100% |
Financial:
|
|
|
Contract sign on
|
|
Completion date
|
|
|
|
|
|
Name of Project: Comilla-Meghnaghat-Haripur 230 kV Transmission Line and Turn in and Turn out at Rampura of existing Ghorasal-Haripur 230 kV Transmission Line Project
|
|
Objective:
|
|
|
Project cost:
|
Local 18045.70 lac taka, Foreign 19387.65 lac taka |
|
Financed by:
|
ADB |
Contractor Name:
|
|
|
Status
|
|
Physical:
|
100% |
Financial:
|
|
|
Contract sign on
|
|
Completion date
|
|
|
|
|
|
Name of Project: Khulna-Ishurdi and Bogra-Barapukuria 230 kV Transmission Line Project
|
|
Objective:
|
|
|
Project cost:
|
|
|
Financed by:
|
ADB,Kfw,NDF,SIDA,PGCB's own fund,Supplier's Credit |
Contractor Name:
|
|
|
Status
|
|
Physical:
|
100% |
Financial:
|
|
|
Contract sign on
|
|
Completion date
|
|
|
|
|
|
Name of Project: Second East-West Electrical Interconnector (Ashuganj-Jamuna Multipurp
|
|
Objective:
|
|
|
Project cost:
|
Local 11988.60 lac taka, Foreign 19858.93 lac taka |
|
Financed by:
|
ADB |
Contractor Name:
|
|
|
Status
|
|
Physical:
|
|
Financial:
|
100% |
|
Contract sign on
|
|
Completion date
|
|
|
|
|
|
Name of Project: Natore-Rajshahi 132 kV Transmission Line
|
|
Objective:
|
|
|
Project cost:
|
|
|
Financed by:
|
PGCB's own fund |
Contractor Name:
|
|
|
Status
|
|
Physical:
|
100% |
Financial:
|
|
|
Contract sign on
|
|
Completion date
|
|
|
|
|
|
Name of Project: Ashuganj-Shahjibazar 132 KV Single Circuit Transmission Line
|
|
Objective:
|
|
|
Project cost:
|
|
|
Financed by:
|
PGCB's own fundc |
Contractor Name:
|
|
|
Status
|
|
Physical:
|
100% |
Financial:
|
|
|
Contract sign on
|
|
Completion date
|
|
|
|
|
|
Name of Project: Noagaon-Niamotpur 132 kV Transmission Line
|
|
Objective:
|
|
|
Project cost:
|
|
|
Financed by:
|
PGCB's own fund |
Contractor Name:
|
|
|
Status
|
|
Physical:
|
100% |
Financial:
|
|
|
Contract sign on
|
|
Completion date
|
|
|
|
|
|