Name of Project: Construction & Extension of Grid Substations including transmission line facilities (Phase-1)
|
|
Objective:
|
To meet the growing demand of respective areas.
|
|
Project cost:
|
Local 36.37 M US$,Foreign 57.29 M US$ |
|
Financed by:
|
ADB & JICA |
Contractor Name:
|
|
|
Status
|
|
Physical:
|
60% |
Financial:
|
|
|
Contract sign on
|
|
Completion date
|
|
|
|
|
|
Name of Project: Three Transmission Lines Project.
|
|
Objective:
|
To meet the demand of Panchagarh, Joypurhat, Magura and Chuadanga |
|
Project cost:
|
Local 24.39 M US$,Foreign 31.94 M US$ |
|
Financed by:
|
ADB |
Contractor Name:
|
|
|
Status
|
|
Physical:
|
84% |
Financial:
|
|
|
Contract sign on
|
|
Completion date
|
|
|
|
|
|
Name of Project: Meghnaghat-Aminbazar 400 kV Transmission Line
|
|
Objective:
|
To evacuate Power from Meghnaghat P/S and to supply reliable power to western part of Dhaka. |
|
Project cost:
|
Local 17.39 MUS$,Foreign 22.86 MUS$ |
|
Financed by:
|
ADB |
Contractor Name:
|
|
|
Status
|
|
Physical:
|
9% |
Financial:
|
|
|
Contract sign on
|
|
Completion date
|
|
|
|
|
|
Name of Project: Aminbazar-Old Airport 230 kV Transmission Line and Associated Substations
|
|
Objective:
|
To supply reliable power and to meet the growing demand of western part of Dhaka city
|
|
Project cost:
|
Local 40.03 MUS$, foreign 53.22 MUS$ |
|
Financed by:
|
ADB |
Contractor Name:
|
|
|
Status
|
|
Physical:
|
29.00% |
Financial:
|
|
|
Contract sign on
|
|
Completion date
|
|
|
|
|
|
Name of Project: Transmission Efficiency Improvement through Reactive Power Compensation at Grid Substations and Reinforcement of Goalpara Substation
|
|
Objective:
|
To maintain reasonable voltage & to reduce Transmission loss.
|
|
Project cost:
|
Local 13.11 M US$, Foreign 20.45 M US$ |
|
Financed by:
|
kfW |
Contractor Name:
|
|
|
Status
|
|
Physical:
|
12% |
Financial:
|
|
|
Contract sign on
|
|
Completion date
|
|
|
|
|
|
Name of Project: Siddhirganj-Maniknagar 230 kV Transmission Line
|
|
Objective:
|
To evacuate the power generated at Siddhirganj & to meet the growing demand of Maniknagar and adjoint area |
|
Project cost:
|
Local 18.82 MUS$, Foreign 32.72 MUS$ |
|
Financed by:
|
WB |
Contractor Name:
|
|
|
Status
|
|
Physical:
|
0.80% |
Financial:
|
|
|
Contract sign on
|
|
Completion date
|
|
|
|
|
|
Name of Project: Evacuation facilities for 1350 MW new initiatives plants of BPDB
|
|
Objective:
|
To build the power evacuation facilities for the upcoming 1350 MW new initiative power plants. |
|
Project cost:
|
|
|
Financed by:
|
PGCB's own fund |
Contractor Name:
|
|
|
Status
|
|
Physical:
|
|
Financial:
|
|
|
Contract sign on
|
|
Completion date
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|